Mainstream Recycling (Apr 2020 – May 2020)
Construction of a 16 m long x 6 m wide x 4 m deep below ground pit with 1.2 m walls above ground in Truganina. Works were completed adjacent to structural walls and required the installation of piling prior to starting. All above-ground walls were off form finish and below-ground walls were sprayed. In addition to the on-site works we also completed the design through our design partner GES.