Roundabout reconstruction at Intersection of Ewing and Barkly Street, Brunswick.  Works included the installation of 80 lin.m of drainage, 250 lin.m of bluestone and concrete kerb and channel, 100 sq.m of footpaths, concrete splitter islands and reconstruction of 600 sq.m of asphalt pavement.  All works completed while maintaining traffic and pedestrian flows and access for local residences.